    We at STEAG always have been driven by one thing: the will to make ever better use of energy. Today we offer services that cover the entire value chain of a modern energy service provider. We thus ensure not only today's supply, but help to advance the transition to the future of energy. Jointly, safely and efficiently.

    Read more

    Valuable contribution to the heating transition

    The pipeline and civil engineering work on Essen’s eastern line district heating expansion project has been completed.

    Essen. STEAG Fernwärme Essen GmbH & Co. KG, a joint venture of Stadtwerke Essen AG and STEAG Fernwärme GmbH, has successfully completed work on Essen’s eastern line district heating expansion project. The pipeline and civil engineering work has been completed in all three construction sections. In the coming weeks, remaining work such as the restoration of surfaces and carriageways and replacement planting will follow. The most recent delay in the implementation of the project was due in particular to the necessary rerouting and difficulties caused by the coronavirus pandemic.

    The last weld on the district heating pipeline in the ‘Osttrasse’ (eastern line) project was completed on March 24, 2022. “We have now brought the core work on a major urban development project to a successful conclusion, and in the coming years it will make a significant contribution to reducing emissions from heating consumption and thus to the success of the heating transition in our city,” as Dr. Peter Schäfer, Managing Director of STEAG Fernwärme Essen, and also Chairman of the Management Board of Stadtwerke Essen, is pleased to report.

    That was the view of Essen’s Mayor Thomas Kufen right from the start of the project: “With the expansion of the district heating system we are ensuring a better quality of life, because the use of climate-friendly district heating significantly improves the carbon footprint of our city. In the spirit of this jointly pursued objective, we are supporting the costly construction phase.”

    ERDF funding
    And because the expansion of the district heating network in Essen is in this respect a significant contribution to the heating transition and climate protection in North Rhine-Westphalia, the construction of the eastern line is also being supported with eight million euros from the European Regional Development Fund (ERDF), awarded by the state government of North Rhine-Westphalia as part of the progres.nrw funding.

    In keeping with these commitments and considering the impact of the work on residents and traffic, all those involved in the project are now pleased with the smooth progress overall, which is an achievement in itself, particularly given the dimensions of the project.

    Successful team performance
    Matthias Ohl, Technical Director of STEAG Fernwärme, puts it in a nutshell: “In terms of planning and implementation, the eastern line as an infrastructure project was as demanding as it was worthwhile for climate protection. In this respect, the investors, construction companies, authorities and agencies involved, as well as our colleagues, deserve a great amount of thanks.” All the more so, as the delay in completion was due to unforeseeable changes in the routing of the line and to the coronavirus pandemic.

    Remaining work in May and June
    Since the beginning of April, the second and third construction sections of the new pipeline network have also been gradually filled with district heating water and vented. “We then gradually ran these sections of the eastern line in trial operation before the final measures were taken to integrate them into the existing network,” says STEAG’s Project Manager Georg Röttgers, explaining the current status of the final work.

    The remaining work is scheduled to take place in the coming weeks. The last construction trenches will be backfilled, and the remaining surfaces and carriageways will be restored. Finally, at the very end of the project, replacement planting will take place for trees that had to give way to the construction work over the past 30 months or so. “Only when the last tree has been planted will the project be truly complete for us. The customers we supply will, of course, be able to receive their climate-friendly district heating at an earlier date,” says Matthias Ohl.

    Aldi Campus and TÜV Nord Campus milestones
    Parts of the new district heating network had already recently gone into operation in connection with commissioning of the first construction phase of the eastern line, when the food discounter Aldi Nord, which is based in Essen and operates worldwide, inaugurated the Aldi Campus which is also supplied by STEAG Fernwärme Essen.

    TÜV Nord also relies on climate-friendly district heating from STEAG. In the autumn of 2021, the TÜV NORD CAMPUS ESSEN was officially opened directly at the new Frillendorf slip road to the A40 motorway. The extensive technology site, where 1,800 people will work in the future, brings together a wide range of competencies. Other buildings in the TÜV Nord portfolio will also be supplied with district heating from STEAG Fernwärme Essen, starting in autumn 2022.

    Further expansion beyond the A 52 firmly planned
    At the same time, Michael Straus, Managing Director of STEAG Fernwärme, confirms that the expansion of the network will continue: “With the successful completion of the Osttrasse project, the foundation stone has been laid for the further expansion of district heating in and for Essen and connection to further parts of the city. With the crossing below the A52 motorway already completed last year, for the first time in the more than 60-year history of district heating in Essen we have created the conditions for connecting districts located south-east of the A52 to the district heating network in the long term.” In this respect, the potential of district heating for local emission reduction is far from exhausted, he said, and work is under way to further improve the carbon footprint of Essen.

    Services

    Energy Services

    Energy Services

    Whether power plants or distributed facilities, whether conventional or renewable energies: we offer tailor-made solutions – from planning and development to implementation and optimization.

    More

    Renewable Energies

    Renewable Energies

    We play an active role in shaping the transition to a sustainable energy mix. We can contribute extensive experience in this field, too, because we already have been relying on renewables worldwide for many years.

    More

    District Heating

    District Heating

    As a regional energy company we supply private households, major customers and real estate companies in North Rhine-Westphalia, Saarland and Poland with environmentally friendly district heating.

    More

    Distributed Energy Supply

    Distributed Energy Supply

    The production of energy at the place it is needed is gaining more and more importance. STEAG New Energies develops tailor-made solutions for industry, municipalities, public utilities and the housing sector.

    More

    Technical Service

    Technical Service

    STEAG Technischer Service handles the complete planning and implementation of all technical services required for plant operation in the area of maintenance.

    More

    Energy Trading & Optimization

    Energy Trading & Optimization

    Trading & Optimization is the trading unit of STEAG: it handles raw material procurement and trading as well as the control and optimization of assets – for us and for external customers.

    More

    Waste Incineration

    Waste Incineration

    The generation of power and heat based on demanding fuels and sophisticated technologies is our core competence. STEAG Waste to Energy bundles the activities in the area of waste incineration.

    More

    Conventional Power Generation

    Conventional Power Generation

    Our safe and highly efficient power plants stand worldwide for the security of supply that consumers and industry need, now and in future.

    More

    Large Battery Systems

    Large Battery Systems

    Our large-scale battery systems maintain voltage and ensure the reliability of supply despite the increasing fluctuations in the power grid. In future they will take on even more tasks.

    More

    Jobs

    Careers

    STEAG is backed by a solid team.

    Read more
    News

    Valuable contribution to the heating transition

    The pipeline and civil engineering work on Essen’s eastern line district heating expansion project has been completed.

    Essen. STEAG Fernwärme Essen GmbH & Co. KG, a joint venture of Stadtwerke Essen AG and STEAG Fernwärme GmbH, has successfully completed work on Essen’s eastern line district heating expansion project. The pipeline and civil engineering work has been completed in all three construction sections. In the coming weeks, remaining work such as the restoration of surfaces and carriageways and replacement planting will follow. The most recent delay in the implementation of the project was due in particular to the necessary rerouting and difficulties caused by the coronavirus pandemic.

    The last weld on the district heating pipeline in the ‘Osttrasse’ (eastern line) project was completed on March 24, 2022. “We have now brought the core work on a major urban development project to a successful conclusion, and in the coming years it will make a significant contribution to reducing emissions from heating consumption and thus to the success of the heating transition in our city,” as Dr. Peter Schäfer, Managing Director of STEAG Fernwärme Essen, and also Chairman of the Management Board of Stadtwerke Essen, is pleased to report.

    That was the view of Essen’s Mayor Thomas Kufen right from the start of the project: “With the expansion of the district heating system we are ensuring a better quality of life, because the use of climate-friendly district heating significantly improves the carbon footprint of our city. In the spirit of this jointly pursued objective, we are supporting the costly construction phase.”

    ERDF funding
    And because the expansion of the district heating network in Essen is in this respect a significant contribution to the heating transition and climate protection in North Rhine-Westphalia, the construction of the eastern line is also being supported with eight million euros from the European Regional Development Fund (ERDF), awarded by the state government of North Rhine-Westphalia as part of the progres.nrw funding.

    In keeping with these commitments and considering the impact of the work on residents and traffic, all those involved in the project are now pleased with the smooth progress overall, which is an achievement in itself, particularly given the dimensions of the project.

    Successful team performance
    Matthias Ohl, Technical Director of STEAG Fernwärme, puts it in a nutshell: “In terms of planning and implementation, the eastern line as an infrastructure project was as demanding as it was worthwhile for climate protection. In this respect, the investors, construction companies, authorities and agencies involved, as well as our colleagues, deserve a great amount of thanks.” All the more so, as the delay in completion was due to unforeseeable changes in the routing of the line and to the coronavirus pandemic.

    Remaining work in May and June
    Since the beginning of April, the second and third construction sections of the new pipeline network have also been gradually filled with district heating water and vented. “We then gradually ran these sections of the eastern line in trial operation before the final measures were taken to integrate them into the existing network,” says STEAG’s Project Manager Georg Röttgers, explaining the current status of the final work.

    The remaining work is scheduled to take place in the coming weeks. The last construction trenches will be backfilled, and the remaining surfaces and carriageways will be restored. Finally, at the very end of the project, replacement planting will take place for trees that had to give way to the construction work over the past 30 months or so. “Only when the last tree has been planted will the project be truly complete for us. The customers we supply will, of course, be able to receive their climate-friendly district heating at an earlier date,” says Matthias Ohl.

    Aldi Campus and TÜV Nord Campus milestones
    Parts of the new district heating network had already recently gone into operation in connection with commissioning of the first construction phase of the eastern line, when the food discounter Aldi Nord, which is based in Essen and operates worldwide, inaugurated the Aldi Campus which is also supplied by STEAG Fernwärme Essen.

    TÜV Nord also relies on climate-friendly district heating from STEAG. In the autumn of 2021, the TÜV NORD CAMPUS ESSEN was officially opened directly at the new Frillendorf slip road to the A40 motorway. The extensive technology site, where 1,800 people will work in the future, brings together a wide range of competencies. Other buildings in the TÜV Nord portfolio will also be supplied with district heating from STEAG Fernwärme Essen, starting in autumn 2022.

    Further expansion beyond the A 52 firmly planned
    At the same time, Michael Straus, Managing Director of STEAG Fernwärme, confirms that the expansion of the network will continue: “With the successful completion of the Osttrasse project, the foundation stone has been laid for the further expansion of district heating in and for Essen and connection to further parts of the city. With the crossing below the A52 motorway already completed last year, for the first time in the more than 60-year history of district heating in Essen we have created the conditions for connecting districts located south-east of the A52 to the district heating network in the long term.” In this respect, the potential of district heating for local emission reduction is far from exhausted, he said, and work is under way to further improve the carbon footprint of Essen.